SEC Tehama EPP – Upgrade of Control Systems for GT8&9

Al Qunfudha, Saudi Arabia • Feb 2022 – Feb 2024

Project Overview
Project OwnerSaudi Electricity Company (SEC-WOA)
Main EPC ContractorSaudi Arabian Engineering Co. (SAECO)
ConsultantSEC Tehama EPP Technical Support Department
Employer / CompanyEnergy Resources Development Company (TAACA)
LocationAl Qunfudha
CountrySaudi Arabia
Technical Information
IndustryPower
Technologies & SystemsControls & Instrumentation, Controls & Protection, DCS, Power Generation, Power Plant
Project TypeRetrofit
Capacity / Specifications2 x 60 MW
StatusCompleted
Start Month / YearFeb 2022
End Month / YearFeb 2024
Project Duration2 Years
The Role

Position / Role: Control Systems Engineer & Projects Leader

Scope of Work

Upgrade of the control systems for GE Gas Turbine Units GT8 & GT9 from Mark-V to Mark-VIe, including system integration, testing and commissioning.

Key Responsibilities

Led the project lifecycle from initiation through final commissioning and hand over; managed the EPC Contractor as Owner’s Project Leader; supervised control-system engineering, installation, integration, testing and commissioning; coordinated interfaces with existing plant systems and operations.

Key Achievements

Successfully completed the GT8 & GT9 control-system upgrade and migration from GE Mark-V to Mark-VIe.

Lessons Learned

Control-system migration in an operating power plant requires careful planning, detailed understanding of the existing system, disciplined configuration management and comprehensive testing. Successful migration depends on close coordination among the Owner, EPC Contractor and operations team, with thorough integration testing and commissioning to ensure continuity of safe and reliable unit operation.