SEC Farasan 132 KV Substation & STATCOM Project

Farasan Islands, Saudi Arabia • Feb 2026 – Aug 2026

Project Overview
Project TimelineFrom Feb 2026 To Aug 2026 → 6 Months
Project OwnerSaudi Electricity Company - WOA
Main EPC ContractorNESMA Infrastructure & Technologies Co.
ConsultantSEC-PDC/ CESI
OEM / Major Equipment SupplierHitachi Energy, TBEA, China, Siemens
Capacity132/33/13.8 KV
StatusCompleted
IndustryPower
Manufacturer Equipment Description
Hitachi Energy 132 kV GIS, 33 kV Capacitor Bank, 13.8 kV Capacitor Bank, SAS & Protection System 132 kV GIS substation equipment, capacitor banks, substation automation, and protection systems for high-voltage power transmission and reactive power compensation.
Siemens 33 kV Switchgear 33 kV medium-voltage switchgear for power distribution, feeder control, switching, isolation, and protection.
NR Electric, China STATCOM System, VSC Converter / Valve System, STATCOM AC Reactors, Charging Resistor, STATCOM Bypass Switching System, STATCOM Control System, STATCOM Protection System, STATCOM Cooling System, Heat Exchangers, Cooling Control / Power Panels Complete STATCOM system based on VSC technology, including power conversion, AC reactors, bypass and charging systems, control and protection, and dedicated cooling infrastructure.
Multi-vendor STATCOM Main Transformers, 13.8 kV Switchgear, 13.8 kV RMU, Auxiliary Transformer, 132 kV CT/PT/SA/DS/ES, 125 V DC System, 48 V DC System, Telecommunication System, 132 kV Power Cables, Power Transformers Auxiliary electrical systems supporting the STATCOM and substation, including transformers, MV switchgear, HV measurement and isolation equipment, DC systems, telecommunications, and power cabling.
The Role

Position / Role: Sr. Electrical Engineer & Projects Manager

Scope of Work

Representing Subcontractor ISGCC providing specialized construction and commissioning support for Main EPC Contractor NIT under project owner Saudi Electricity Company

Key Responsibilities

Key Achievements

Successful completion of assigned scope within approved budget and time schedule while ensuring quality compliance.